What Next

With construction underway the line should be operational by early 2009.

Key Project Milestones:


Milestones Progress Completion Date
TWA application submitted CompletedJuly 2002
Public Inquiry CompletedJanuary 2003
Powers approved CompletedFebruary 2004
Signed contract for works CompletedJune 2005
Construction commenced CompletedJune 2005
Launch of the Tunnel Boring Machine CompletedApril 2006
First tunnel complete CompletedDecember 2006
Second tunnel complete CompletedJuly 2007
Testing and commissioning commences CompletedJune 2008
Station works and intervention shaft complete Due to be completedSeptember 2008
Completion - Opening of the new route Due to be completedEarly 2009
 