What Next

Key Project Milestones:


Milestones Progress Completion Date
TWA application submitted CompletedAugust 2005
Public Inquiry CompletedMarch 2006
TWA approved CompletedOctober 2006
Contract awarded for enabling works CompletedJanuary 2007
Contract awarded for main construction works CompletedJune 2007
Completion of enabling works CompletedApril 2009
Station construction complete and train testing starts: Due to be completedSpring 2010
Opening of new route Due to be completedSummer 2010