Docklands Light Railway - Shadwell Station Improvements

Skip to navigation

What Next

Milestones Progress Completion Date
Phase 1 works start of construction Completed July 2006
Phase 1 works completed Completed October 2006
Phase 2 works start of construction Completed November 2006
Planning application submission for phase 3 works Completed May 2007
Phase 3 application approval Completed August 2007
Phase 2 works completed Completed October 2007
Phase 3 works start of construction Completed August 2007
Phase 3 works completed Completed April 2008
 