Docklands Light Railway - Phase 2: Capacity Enhancements

Skip to navigation

What Next

The proposed project timetable is as follows:


Milestones Progress Completion Date
Public consultation and detailed scheme development CompletedMarch – May 2006
Submit application for Order under Transport and Works Act 1992 (TWA) to authorise works CompletedAugust 2006
Public Inquiry CompletedMarch 2007
TWA Powers approved CompletedSeptember 2007
Expected signed contract for works Due to be completedSpring 2008
Expected start of construction Due to be completedMid 2008
Expected completion Due to be completedMid 2010
 