What Next

Anticipated key project milestones:


Milestones Progress Completion Date
Passenger and stakeholder consultation CompletedSeptember 2007
Further design CompletedAutumn 2007
Submit applications for Planning Approval CompletedSeptember 2007
Planning approval CompletedJanuary 2008
Contract awarded CompletedJanuary 2008
Receive Network Rail approvals CompletedMay / June 2008
Start construction of bridge link CompletedAugust 2008
Start construction on C2C building CompletedAugust 2009
Footbridge opens CompletedNovember 2009
New eastern station entrances open Due to be completedDecember 2009

 