What Next


Milestones Completion Date
Planning application submitted CompletedNovember 2005
Confirmation of the scheme CompletedFebruary 2006
Appointment of contractor CompletedOctober 2006
Start of works CompletedNovember 2006
Station opened Completed8 December 2007
 