Docklands Light Railway - Three-carriage Capacity Enhancement Project

Skip to navigation

What Next

Key Project Milestones:


Milestones Progress Completion Date
Three-carriage Capacity Enhancement: Bank to Lewisham
TWA Application Submitted CompletedJune 2004
Public Inquiry CompletedFebruary 2005
Powers approved CompletedOctober 2006
 
Three-carriage Capacity Enhancement: Poplar to Stratford & Beckton
TWA Application submitted CompletedAugust 2006
Public Enquiry CompletedMarch 2007
Powers approved CompletedSeptember 2007
 
Construction
Start of Construction CompletedMay 2007
Tower Gateway temporary closure CompletedJune 2008 - Spring 2009
Reduced service Crossharbour to Lewisham CompletedJune 2008 - August 2008
DLR Bank platforms temporary closure December 2009
Expected completion of three-carriage upgrade works Early 2010
 