Go to: Main Content Go to: Navigation

Transport for London

Docklands Light Railway - Three-carriage Capacity Enhancement Project

Skip to navigation

What Next

Key Project Milestones:


Milestones Progress Completion Date
Three-carriage Capacity Enhancement: Bank to Lewisham
TWA Application Submitted CompletedJune 2004
Public Inquiry CompletedFebruary 2005
Powers approved CompletedOctober 2006
 
Three-carriage Capacity Enhancement: Poplar to Stratford & Beckton
TWA Application submitted CompletedAugust 2006
Public Enquiry CompletedMarch 2007
Powers approved CompletedSeptember 2007
 
Construction
Start of Construction CompletedMay 2007
Tower Gateway temporary closure CompletedJune 2008 - Spring 2009
Reduced service Crossharbour to Lewisham CompletedJune 2008 - August 2008
DLR Bank platforms temporary closure CompletedDecember 2009 - January 2010
Three-carriage trains run between Bank and Lewisham CompletedEarly 2010
Three-carriage construction complete on Beckton route Early 2011
 

Back   Top

Navigation

You are here:
CorporateModes of transportDocklands Light RailwayDevelopment ProjectsRailway Enhancements