Docklands Light Railway - Capacity Enhancement (3-car)

Skip to navigation

What Next

  • Key Project Milestones: 

    Milestones Progress Completion Date
    Three-carriage Capacity Enhancement: Bank to Lewisham
    TWA Application Submitted June 2004Completed 
    Public Inquiry February 2005Completed 
    Powers approved October 2006Completed 
     
    Three-carriage Capacity Enhancement: Poplar to Stratford & Beckton
    TWA Application submitted August 2006Completed 
    Public Inquiry March 2007Completed 
    Powers approved September 2007Completed 
     
    Construction
    Start of Construction May 2007Completed 
    Tower Gateway temporary closure June 2008 - Spring 2009Completed 
    Reduced service Crossharbour to Lewisham June 2008 - August 2008Completed 
    DLR Bank platforms temporary closure December 2009 - January 2010Completed 
    3-car trains run between Bank and Lewisham Early 2010Completed 
    3-car construction complete on Beckton route 2011